Oct 13, 20171 min read
Ailed Mazas - Day 23
Hours worked: 4 Tasks completed: Red Lines for The Chapel at the Sanctuary AXP credits: Practice Management
Hours worked: 4 Tasks completed: Red Lines for The Chapel at the Sanctuary AXP credits: Practice Management
LESSONS LEARNED: This week I started learning a lot about the importance of code that I have not understood to this level before. The...
TIME WORKED: 4 hrs. TASKS PERFORMED: Today I worked on elevations for one project, and then I switched to another project and began a new...
Meet with Duncan and some of the staff member of Matenoia. And we visited some of the projects we are doing. Talked about some of the...
After going through the list of the core values with my mentor, he told me a short about the Excellence - responsive service. He had a...
When I was uploading images of the residential projects to the website using the website design software online, it only allowed me to...
I was very impressed when I had the construction site visit in Kiawah Island, SC, and my mentor said it is one of the most rich area in...
Had a little trouble while fixing the about us page of the firm on the current website, I was trying to fix the font type, the font size,...
It was interesting to look through all the previous projects they did in the past and had a small lesson to learn how the website program...
I had a small conference meeting on my first day with my mentor and my coworkers about current projects they are currently working on....
This week I learned how long the design process takes. I further worked on the Tennessee house, adding the structural systems. While...
This week was shorter, with my mentor being out of town on Thursday. Tuesday I finished floor plans for the previous project I was...
This week was more difficult for me. The house I was making edits to in Revit was set up vastly different than the construction...
This week really focused on honing in my skills in Revit and testing my ability to quickly make changes and additions to a model. I...
This week along side developing a Revit model I got to attend 2 site visits which were informative to me. I always appreciate seeing the...
Beginning work at a firm quickly put into perspective what of school has been essential, finally starting to use my skills in the real...
Hours: 8 Today I worked on a physical model that will be presented to a client. After taking a trip to gather supplies I began hand...
Hours: 6 Today I began working out the structure for the Revit model of the house in Tennessee. It started off tough tackling the roof...
This week, we had our second deadline for the Citadel Mall project. This meant that the days before it were hectic but after I got to...