Michael Mioux - Day 35
Hours worked: 4.5 Tasks performed: Revit Work accomplished: Kept adding windows to Sedgefield, adjusted dimensions of walls to make more...
Michael Mioux - Week 9 Lessons Learned
After the walkthrough of Sedgefield school on Wednesday, I realized that projects can quickly grow in scope. What was supposed to be a...
Michael Mioux - Day 34
Hours worked: 6.25 Tasks performed: Revit Work accomplished: Finished placing the walls in Sedgefield school. Started adding windows in...
Michael Mioux - Day 33
Hours worked: 5.5 Tasks performed: Revit and walkthrough Work accomplished: Created more walls for Sedgefield school (there’s a lot)....
Michael Mioux - Day 32
Hours worked: 4.5 Tasks performed: Revit Work accomplished: Continued creating walls for Sedgefield school. It’s unfortunate we don’t...
Michael Mioux - Day 31
Hours worked: 4.25 Tasks performed: Revit Work accomplished: Typed meeting notes from last week. Started setting up a new Revit project...
Michael Mioux - Week 8 Lessons Learned
My boss started telling me about the transition process that will happen when the leave the company. It was interesting to hear how that...
Michael Mioux - Day 30
Hours worked: 7.25 Tasks performed: Meeting with contractor Work accomplished: Met with Cummings, a construction company in North...
Michael Mioux - Day 29
Hours worked: 4.25 Tasks performed: Revit Work accomplished: Started placing doors, created schedule for doors and key schedule for the...
Michael Mioux - Day 28
Hours worked: 6 Tasks performed: Revit Work accomplished: Edited some doors in Lambs revit file, started and finished modeling walls for...
Michael Mioux - Day 27
Hours worked: 4.25 Tasks performed: Meeting notes Work accomplished: Typed mentor’s meeting notes from the previous week for the new...
Michael Mioux - Week 7 Lessons Learned
I learned this week there are several key players in a project. The coordination can be cumbersome, but extremely important when...
Michael Mioux - Day 26
Hours worked: 8.25 Tasks performed: Revit Work accomplished: Continued to trace cad drawings of the two schools in Revit. Basically I am...
Michael Mioux - Day 25
Hours worked: 4.25 Tasks performed: Attended consultant meeting Work accomplished: Met with structural, civil, landscape, and electrical...
Michael Mioux - Day 24
Hours worked: 5.5 Tasks performed: Meeting Work accomplished: Today I met with the members of the Charleston County School district for a...
Wan Lam Ng - Week 13
This week was my final week to work at Thomas and Denzinger. I did enjoyed and learned a lot working in this office and I wish that I...
Wan Lam Ng - Week 12
This week I was continued to work on the spread sheet for the construction document. I had learned that there were a lots of sheet...
Wan Lam Ng - Week 11
This week I was cleaning up the plan, sections and elevations, hided all the unnecessary elements that were on the plans. I had learning...
Wan Lam Ng - Week 10
This week I had to fix one of their old physical model that was been broken for a while. It was a fun and challenge puzzle to fix. This...