Sep 26, 20171 min read
DAY 17
TIME WORKED: 4 hrs. TASKS PERFORMED: Today I finished the redlines for the residential set I have been working on for a few days. We also...
TIME WORKED: 4 hrs. TASKS PERFORMED: Today I finished the redlines for the residential set I have been working on for a few days. We also...
Time Worked: 4 Hours Tasks Performed: Fixing model after getting outline from survey Work Accomplished: Fixed interior walls and...
Time Worked: 2 Hours Tasks Performed: Specs and model Work Accomplished: Worked on the specs of the stadium project. Also, fixed the...
Time Worked: 4 Hours Tasks Performed: Preparation for BAR Work Accomplished: Printed and filled all the forms for the BAR meeting and...
Time Worked: 4 Hours Tasks Performed: Rendered Elevations Work Accomplished: Tested materials and colors for exterior on elevations for...
Hours Worked: 4 Tasks Performed: I sat in on the weekly morning meeting where we discussed all of the projects currently happening in the...
I learned how important site context and the right view is to showing exactly what we want to show to a client. A little to the left, a...
Time Worked: 4 Hours Tasks Performed: Photoshop Work Accomplished: I am looking at our landscape plan for the Baxter Patrick library and...
Time Worked: 2 Hours Tasks Performed: Public housing research Work Accomplished: I researched different public housing retrofit...
Time Worked: 4 Hours Tasks Performed: Beau Clowney Architects has a new full time hire, and I moved from my old work station to a new...
This week I learned how important it is to understand a place before jumping straight into designing. By sitting down and talking with my...
This week I learned about some of the other tasks that come with owning an architecture firm such as preparing for a hurricane. Though...
Through sitting in on some meetings this week I learned how much coordination it takes between architects and consultants on even the...
I have many takeaways from my first week back working at Rush Dixon Architects. Just sitting in on the weekly morning meeting made me...
7.0 HOURS: Continued working on 3D printing preparation task - finished modeling buildings and began to model an assortment of boats for...
4.0 HOURS: Prepared 3D revit models of two buildings for 3D printing, for a site model of a marina master plan. AXP: 4.0 HOURS Project...
5.0 HOURS: Continued working on residential building project in Savannah, GA. Created massing model in Revit updated with altered...
9.5 HOURS Created a parametric key plan for perimeter floor plans on a residential project in downtown Charleston. AXP: 9.5 HOURS Project...
8.5 HOURS: Arranged sheets from exterior envelope project. Updated portions of model. Organized design precedents and helped pick...
3.5 HOURS: Continued working on 3D modeling project for building envelope in Mount Pleasant, updated sections based on new redlines. AXP:...