Oct 10, 20171 min read
Shane Lenard – Day Ten
Date: 9/8/17 Hours: 1.5 AXP: Programming & Analysis Task Performed: Worked on CSL Pittsburg, PA 563 Rodi Rd/Carson St. 564 as-builts....
Date: 9/8/17 Hours: 1.5 AXP: Programming & Analysis Task Performed: Worked on CSL Pittsburg, PA 563 Rodi Rd/Carson St. 564 as-builts....
Date: 9/7/17 Hours: 4 AXP: Programming & Analysis Task Performed: Worked on CSL Pittsburg, PA 563 Rodi Rd/Carson St. 564 as-builts. Work...
Date: 9/6/17 Hours: 4 AXP: Programming & Analysis Task Performed: Worked on CSL Pittsburg, PA 563 Rodi Rd as-built. Work Accomplished: We...
Date: 9/5/17 Hours: 3.5 AXP: Practice Management/ Programming & Analysis Task Performed: Worked on CSL Pittsburg, PA 563 Rodi Rd...
Date: 8/31/17 Hours: 5 AXP: Practice Management / Project Development and Documentation Task Performed: Worked on DRVIT details. Work...
Date: 8/30/17 Hours: 4 AXP: Project Development and Documentation Task Performed: Worked on DRVIT details. Work Accomplished: Worked EIFS...
Hours Worked: 4 hours Tasks Completed: Today I took measurements for the physical model in order to purchase materials tomorrow. There...
Date: 8/29/17 Hours: 4 AXP: Project Development and Documentation Task Performed: Worked on DRVIT details. Work Accomplished: Worked EIFS...
Date: 8/28/17 Hours: 3 AXP: Practice Management / Project Development and Documentation Task Performed: Worked on DRVIT details. Work...
Date: 8/24/17 Hours: 4 AXP: Project Development and Documentation Task Performed: I Helped Michael with FBC Port Lavaca CDs. Work...
Date: 8/23/17 Hours: 4.5 AXP: Practice Management / Programming & Analysis Task Performed: Worked on CSL Charlotte 418 as-built. Work...
Hours Worked: 4 Tasks Performed: Today I was introduced to the 667 King St. project. It will be my job to complete a physical site model...
Hours worked: 4 Tasks completed: Ran calculations of impervious surface area for a private residence in the Isle of Palms; the client is...
Time Worked: 4 hours Tasks Performed: Orientation/Setup Lessons Learned: Today was my first day at McMillan Pazdan Smith's Charleston...
Time Worked: 4 hours Tasks Performed: Finished up the program diagram for the Clarendon health Systems Nursing Home. Lessons Learned: I...
Hours Worked: 4 Tasks Completed: Today, Laura and I worked together to finish up the Citadel Mall site plan. It was a lot of catching...
9 OCTOBER 2017, MONDAY – DAY 23 TIME: 4 HRS AXP HOURS: Project development and documentation I continue finishing the interior finishing...
6 OCTOBER 2017, FRIDAY – DAY 22 TIME: 4 HRS AXP HOURS: Project development and documentation Today I get to work with the Interior team...
4 OCTOBER 2017, WEDNESDAY – DAY 21 TIME: 4 HRS AXP HOURS: Project planning and design Today I was asked to do a research on the pedestal...
3 OCTOBER 2017, TUESDAY – DAY 20 TIME: 4 HRS AXP HOURS: Project Management Continued to draft the MOM's in the required format. Had a...