Monday, Oct 23, 2017

Duration: 3 hours.


After discussing tasks and upcoming projects during the weekly meeting, I work on a lighting schematic plan of the existing building at the brewery site. Putting this together is interesting since I'm using a moving video recording of the ceiling structure as reference. This project is getting ready for submittal tomorrow.

I also briefly look at code requirements affecting toilet fixtures in the project happening below our office (at 721 King St ).


Tasks completed: Lighting plan; weekly meeting

AXP credits: TBD


Project: Banyan Roots Brewing Company

Location: 1038 White Street SW, Atlanta, Georgia

Type: brewpub

Phase: design review submittal


So I counted lights today.


Recent Posts

See All
Michael Mioux - Day 35

Hours worked: 4.5 Tasks performed: Revit Work accomplished: Kept adding windows to Sedgefield, adjusted dimensions of walls to make more...

 
 
 
Michael Mioux - Day 34

Hours worked: 6.25 Tasks performed: Revit Work accomplished: Finished placing the walls in Sedgefield school. Started adding windows in...

 
 
 
Michael Mioux - Day 33

Hours worked: 5.5 Tasks performed: Revit and walkthrough Work accomplished: Created more walls for Sedgefield school (there’s a lot)....

 
 
 

Comments


bottom of page