top of page

VISHNU — DAY 26

  • Oct 15, 2017
  • 1 min read

Hours worked: 4


Realizing that we had left out some parts, Luke asks us to go back to 162 Spring St. first thing in the morning, and get those measurements. On returning, I update the elevations, removing some windows and adding in outlines of the neighboring barn structure.


Tasks completed: site visit and measurements, elevation updates

AXP credits: TBD

Project: Fish Hopkins - 162 Spring St.

Location: 162 Spring St, Charleston, SC

Type: residential

Phase: design revisions


[add photos from site visit]

Recent Posts

See All
Michael Mioux - Day 35

Hours worked: 4.5 Tasks performed: Revit Work accomplished: Kept adding windows to Sedgefield, adjusted dimensions of walls to make more...

 
 
 
Michael Mioux - Day 34

Hours worked: 6.25 Tasks performed: Revit Work accomplished: Finished placing the walls in Sedgefield school. Started adding windows in...

 
 
 
Michael Mioux - Day 33

Hours worked: 5.5 Tasks performed: Revit and walkthrough Work accomplished: Created more walls for Sedgefield school (there’s a lot)....

 
 
 