Hours worked: 4.5


A very short week 3 begins.

I'm back after my short break in Clemson. I get started with aligning the SketchUp elevation exports of 663 Blv. with the elevation CAD file, then move on to work on red lines for Foundry Alley (Lots 8&9).

Luke and I visit the Gaillard Center to hand over some drawings for approval. I meet Alex who represents the BAR and DRB. We speak to him about revisions to 162 Spring St. and Foundry Alley 81 Nassau St.


Tasks completed: set up elevations file, red lines, visit to BAR/DRB

AXP credits: TBD

Project: Sunspring Partners 663 Blvd. - 4th Ward

Location: Boulevard NE, Atlanta, GA

Type: residential

Phase: design


Project: Foundry Alley Lots 8&9

Location: Nassau St, Charleston, SC

Type: residential

Phase: design revisions

Recent Posts

See All
Michael Mioux - Day 35

Hours worked: 4.5 Tasks performed: Revit Work accomplished: Kept adding windows to Sedgefield, adjusted dimensions of walls to make more...

 
 
 
Michael Mioux - Day 34

Hours worked: 6.25 Tasks performed: Revit Work accomplished: Finished placing the walls in Sedgefield school. Started adding windows in...

 
 
 
Michael Mioux - Day 33

Hours worked: 5.5 Tasks performed: Revit and walkthrough Work accomplished: Created more walls for Sedgefield school (there’s a lot)....

 
 
 