Tasks: Floor plan edits

AXP: Project development and documentation

Today I finished creating two floor plan options for the TCL renovation. I completed the spacial changes then added in needed details to show the client what the space would be like; for example adding in the pieces that would be demolished and furniture to the new rooms. After this I moved back into the Indigo Hall Augusta projects and began working on the unit floor plans. This required mostly annotation changes but the major piece was changing the type of exterior doors along with their fire rating.

Recent Posts

See All
Michael Mioux - Day 35

Hours worked: 4.5 Tasks performed: Revit Work accomplished: Kept adding windows to Sedgefield, adjusted dimensions of walls to make more...

 
 
 
Michael Mioux - Day 34

Hours worked: 6.25 Tasks performed: Revit Work accomplished: Finished placing the walls in Sedgefield school. Started adding windows in...

 
 
 
Michael Mioux - Day 33

Hours worked: 5.5 Tasks performed: Revit and walkthrough Work accomplished: Created more walls for Sedgefield school (there’s a lot)....

 
 
 