Hours: 4

Tasks: Renovation floor plans

AXP: Project documentation and development

Today I began looking at the floor plan of a building at the Technical College of the Lowcountry. We are working to remodel an area that is currently a kitchen and creating a corridor and new offices for the faculty. Most of the morning was spent drawing the existing floor plan from an old image we had into Cad. Then we began looking at a few options for the layout of the new spaces.

Recent Posts

See All
Michael Mioux - Day 35

Hours worked: 4.5 Tasks performed: Revit Work accomplished: Kept adding windows to Sedgefield, adjusted dimensions of walls to make more...

 
 
 
Michael Mioux - Day 34

Hours worked: 6.25 Tasks performed: Revit Work accomplished: Finished placing the walls in Sedgefield school. Started adding windows in...

 
 
 
Michael Mioux - Day 33

Hours worked: 5.5 Tasks performed: Revit and walkthrough Work accomplished: Created more walls for Sedgefield school (there’s a lot)....

 
 
 