Perry Hammond - Day 14
- Sep 28, 2017
- 1 min read
Updated: Oct 5, 2017
Time Worked: 4 hours
Tasks Performed: Drafting and modeling Walnut Street Storage building.
Work Accomplished: Today I adjusted and added several components to the building sections and wall sections. I changed ceiling heights and drew in a ResinDek floor, while researching some specs and info on this flooring system.
Lessons Learned: On a project like this, space is maximized by running MEP systems exposed below the ceiling/floor structure.
Comments