Hours worked: 3.5

Tasks performed: Punch list + Revit changes + adding civil data

Work accomplished: Typed up the punchlist to send over to the general contractor for James Island Christian School. Began to work with Jerry and Dave on best practices when it comes to introducing civil into Revit as well as what my opinion was on the order of operations when it came to sharing the model with the other architecture firm.


AXP credits: Construction Admin. / Project Management

Name of Project: James Island Christian school / Baxter Patrick James Island Library

Location: Charleston, SC / Charleston, SC

Type of Project: Renovation / New Construction

Phase of Design or Construction: Construction Admin. / Design Development

Recent Posts

See All
Michael Mioux - Day 35

Hours worked: 4.5 Tasks performed: Revit Work accomplished: Kept adding windows to Sedgefield, adjusted dimensions of walls to make more...

 
 
 
Michael Mioux - Day 34

Hours worked: 6.25 Tasks performed: Revit Work accomplished: Finished placing the walls in Sedgefield school. Started adding windows in...

 
 
 
Michael Mioux - Day 33

Hours worked: 5.5 Tasks performed: Revit and walkthrough Work accomplished: Created more walls for Sedgefield school (there’s a lot)....

 
 
 